Biopharmaceutical

New Sterile Vaccine Fill Finish Facility, Pfizer

DPS executed engineering, design and procurement for a new 5,000 sq.m vial fill finish facility at Pfizer Puurs, Belgium.
About this project

DPS executed engineering, design and procurement for a new 5,000 sq.m vial fill finish facility at Pfizer Puurs, Belgium. This facility was designed to produce over 50 million vials a year of a vaccine product. The facility is a standalone segregated facility with scope for expansion to accommodate future vaccine products and was designed for a cold chain product to facilitate the filling of single dose and multi-dose vials in a high speed isolated filling line. DPS also provided key project resources through the construction, commissioning and verification phase.

Some of the key attributes of the facility were:

  • Low cost of goods achieved through lean facility design
  • High volumes (> 80M vials per annum) ; maximise use of process modelling to ensure optimal equipment sizing and cycle time
  • Flexibility to manage change in demand and mix of single and multi-dose
  • Challenging process; investigations on manufacturing strategy ongoing through the design
  • Balance of Segregation and Integration with existing site
  • Automation – fully integrated automation system and MES
  • Expandability
  • Sustainability – energy efficiency and operational strategy were early phase considerations
  • Aggressive Schedule – 18 months from start of construction to product batches
  • ASTM E2500 Verification Strategy

The installation included a multi-vessel formulation suite and isolated filling line with automated materials handling system as well as all standalone clean utilities and tie in to existing black utility systems.

Tell us about your project

and discover how DPS can help you today